Company |
Kampot Port Co., Ltd |
Company profile |
The company was registered as an investment company and was approved in principle for an international port investment project in September 2005, and received permission to pave the road to the port construction site in February and March 2006. . |
Registration investment capital |
USD 100,000,000 |
Company registration date |
10-Oct-05 |
Company registration code |
27,310 |
Director |
Venh Hour |
Director residence |
Cambodia |
Company address |
Koh Touch, Kampot, Kampot |
Status of the EIA reports |
Initial Environmental and Social Impact Assessment |
State agency |
Ministry of Economy and Finance
Ministry of Land Management, Urban Planning and Construction |
Site |
It is located in Village Kilo 12, Prek Touch Commune and Rolous Village, Boeung Touk Commune, Teuk Chhou District, Kampot Province, which is a coastal area and is located about 1 km down from National Road No. 3 with an area of about 1,449.33hectares. |
Village |
Kilo 12 and Rolous |
Commune |
Prek Touch and Boeung Touk |
District |
Teuk Chhou |
Province |
Kampot |
Contract duration |
Not found |
Size in Hectare |
1449.33hectares |
Type of concession |
International Port Project |
EIA company |
CES Co., Ltd. |
Backgrounds of EIA company |
Not found |
Address of EIAs company |
# 56B, Street 230, Sangkat Teuk Laak 3, Khan Toul Kork, Phnom Penh. Phone: 023 210 313, Email info@ces.com.kh |
Relevants law |
Law on environmental protection and natural resources management
Law on fishery
Law on water resource management
Sub-degree on water pollution control
Sub-degree on solide waste management
Sub-degree on environmental impact assessment
Sub-degree on air pollution and noise disturbance
Sub-degree on establshment of special economic zone
Sub-degree on establishment of the sand resources management committee |
Revenues and expenditures |
Not found |
Social alnd environmental impacts |
The project has positive impacts such as:
1. During the implementation of the project can provide jobs for some locals and immigrants
2. The more crowded the landfill area, the more convenient it is to facilitate the shopping activities of the people nearby.
3. May lead to improvement in water quality due to the increase in water velocity, leading to flooding with water along the coast. Currently, the water zone is calm.
4. This pump has packed the meat for filling the filling area.
5. Establish shipping lanes that allow large ships to enter and exit
6. By pumping the slate and filling it in the filling area, this will be a big boost for the Kampot Special Economic Zone and the international port to emerge soon. |
Employment opportunity |
In this project, the company needs about 100 local workers and about 300 foreign workers. |
Public participation |
Ministry of Environment
Department of Environment
Fisheries administration district
Department of industry mine and energy
Department of water resource and meteorology
Department of land management urban planning and construction
Teuk Chhou district authority
Boeung Touk commune authority
Koh Touch commune authority
Prek Tnaot commune authority
Kamport Port Company
CES Co., Ltd |
Land converted from |
The government has allocated 1,000 hectares of land in Kilo 12 village, Koh Touch commune and Boeung Chhouk commune, Kampot district, Kampot province to develop the international port and Kampot special economic zone in proportion to the state's share of 30% of the land and Kamport Port Company shared 70% of the land size. |
Environmental management plan |
The general process of environmental management planning in the project area includes:
1. Data collection and analysis by the project owner or project consultant
2. Preparation of monthly, quarterly and annual reports made by the project owner or project consultant
3. Receipt of reports and implementation of inspections and recommendations for reports by the Ministry or Department of Environment and relevant institutions.
As for the budget, the general preparation and management of the environmental management plan depends on the actual situation when the project is operational. |
Development plan |
The company plans to set up a social fund for environmental impacts to facilitate people's livelihoods, such as:
1. Establish a fund for the restoration of environmental resources
2. Fund for the Restoration of People's Livelihoods
3. Fund for Social Infrastructure. |
Mitigation strategies |
The report covers measures to reduce environmental and social impacts in three phases: pre-implementation, operational and project completion stages, and focuses on physical, biological and socio-economic resources. |
Environmental and social funds |
US$ 6,000,000 |
EIA publication year |
2010 |