• Total Service charges for electricity hook up and disconnection from Electricity of Cambodia (EDC) listed: 32
Map ID
Service supply of EDC
Type of customer
Electric intensity (Ampere)
Hookup fee (Riel)
Booking fee (Riel)
Overall service fee (Riel)
Processing time
Reference
1
Apply for electricity connection from public distribution grid
Residential/administrative building
1x5
31,000
31,000
62,000
15 days (Working day)
2
Apply for electricity connection from public distribution grid
Residential/administrative building
1x10
62,000
62,000
124,000
15 days (Working day)
3
Apply for electricity connection from public distribution grid
Residential/administrative building
1x20
228,000
123,000
351,000
15 days (Working day)
4
Apply for electricity connection from public distribution grid
Residential/administrative building
1x32
368,000
394,000
762,000
15 days (Working day)
5
Apply for electricity connection from public distribution grid
Residential/administrative building
1x63
736,000
775,000
1,511,000
15 days (Working day)
6
Apply for electricity connection from public distribution grid
Residential/administrative building
3x32
1,104,000
1,181,000
2,285,000
45 days (Normal day)
7
Apply for electricity connection from public distribution grid
Residential/administrative building
3x40
1,368,000
1,476,000
2,844,000
45 days (Normal day)
8
Apply for electricity connection from public distribution grid
Residential/administrative building
3x63
2,208,000
2,325,000
4,533,000
45 days (Normal day)
9
Apply for electricity connection from public distribution grid
Residential/administrative building
3x100
3,300,000
3,690,000
6,990,000
45 days (Normal day)
10
Apply for electricity connection from public distribution grid
Business/handicraft
1x5
31,000
123,000
154,000
15 days (Working day)
11
Apply for electricity connection from public distribution grid
Business/handicraft
1x10
62,000
246,000
308,000
15 days (Working day)
12
Apply for electricity connection from public distribution grid
Business/handicraft
1x20
228,000
492,000
720,000
15 days (Working day)
13
Apply for electricity connection from public distribution grid
Business/handicraft
1x32
368,000
787,000
1,155,000
15 days (Working day)
14
Apply for electricity connection from public distribution grid
Business/handicraft
1x63
736,000
1,550,000
2,286,000
15 days (Working day)
15
Apply for electricity connection from public distribution grid
Business/handicraft
3x32
1,104,000
2,362,000
3,466,000
45 days (Normal day)
16
Apply for electricity connection from public distribution grid
Business/handicraft
3x40
1,368,000
2,952,000
4,320,000
45 days (Normal day)
17
Apply for electricity connection from public distribution grid
Business/handicraft
3x63
2,208,000
4,650,000
6,858,000
45 days (Normal day)
18
Apply for electricity connection from public distribution grid
Business/handicraft
3x100
3,300,000
7,380,000
10,680,000
45 days (Normal day)
19
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
1x5
31,000
164,000
195,000
15 days (Working day)
20
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
1x10
62,000
328,000
390,000
15 days (Working day)
21
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
1x20
228,000
656,000
884,000
15 days (Working day)
22
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
1x32
368,000
1,050,000
1,418,000
15 days (Working day)
23
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
1x63
736,000
2,066,000
2,802,000
15 days (Working day)
24
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
3x32
1,104,000
3,149,000
4,253,000
45 days (Normal day)
25
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
3x40
1,368,000
3,936,000
5,304,000
45 days (Normal day)
26
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
3x63
2,208,000
6,199,000
8,407,000
45 days (Normal day)
27
Apply for electricity connection from public distribution grid
Renting house/embassy/hotel
3x100
3,300,000
9,840,000
13,140,000
45 days (Normal day)
28
Disconnect-Reconnect electricity due to late monthly payment
Low voltage
-
-
-
10,000
1 time
29
Disconnect-Reconnect electricity due to late monthly payment
High voltage
-
-
-
20,000
1 time
30
Postpone using temporarily
All customers & all size of electric intensity
-
-
-
40,000
1 time
31
Review and verification of electricity meter
Residential
-
-
-
5,000
1 time
32
Review and verification of electricity meter
Non-residential
-
-
-
10,000
1 time