Techo International Airport ready to be launched in mid-2025
As of the end of July 2024, the construction project of Techo International Airport has achieved more than 80% with a total cost of about 1.2 billion dollars and is scheduled to be completed by the end of 2024. ...
Khmer Times Staff
https://www.khmertimeskh.com/501552145/techo-international-airport-ready-to-be-launched-in-mid-2025/
Techo international airport’s phase 1 on final leg of construction
The new Phnom Penh airport, Techo International Airport’s (TIA) $1.5 billion phase one is 78 percent complete as of June 24, with $1.13 billion used so far, according to joint venture firm Cambodia Airport Investment Co Ltd (CAIC) on Monday. ...
Sangeetha Amarthalingam
https://kiripost.com/stories/techo-international-airports-phase-1-on-final-leg-of-construction
Thailand’s PTT Oil plans aviation fuel depot
Public-listed Thai conglomerate PTT Oil and Retail (OR) will be investing $100 million to develop an oil depot for aviation refuelling at Techo International Airport (TIA), Phnom Penh’s new airport, where first phase operation is scheduled in mid 2024. ...
May Kunmakara
https://www.phnompenhpost.com/author/may-kunmakara/17732
Phnom Penh’s new Techo International Airport scheduled to commence operations by early 2025
The Techo International Airport (TIA), whose construction is about 50 percent complete now, is scheduled to commence in early 2025. ...
Khmer Times Staff
https://www.khmertimeskh.com/501299512/techo-international-airport-scheduled-to-commence-operations-by-early-2025/
Spending on capital’s new airport nears $700M: SSCA
Nearly $700 million has been spent on the new $1.5 billion Techo International Airport (TIA), the main construction work on which has reached 46 per cent as of March 31, motivated by positive tourism growth, according to a senior civil aviation official. ...
Rann Reuy
https://www.phnompenhpost.com/business/spending-capitals-new-airport-nears-700m-ssca
Techo International Airport construction progress on track
The construction of Cambodia’s new international airport has been on track on its construction progress, according to government officials and will soon be 50 percent completed. State Secretariat of Civil Aviation (SSCA) spokesman and undersecretary of state Sin Chansereyvutha spoke to local news and gave ...
Khmer Times Staff
https://www.khmertimeskh.com/501233376/techo-international-airport-construction-progress-on-track/
New int’l airport nearly half complete as travel industry returns to life
Construction of a new airport that is slated to serve the capital has passed the 43 per cent completion mark, raising prospects for a proper recovery in the civil aviation and tourism sectors as international travellers return to the Kingdom in increasingly large numbers. ...
May Kunmakara
https://www.phnompenhpost.com/business/new-intl-airport-nearly-half-complete-travel-industry-returns-life